Question 7
« on: April 20, 2009, 02:16:18 PM »
QUESTION 7
The drawing below shows the plan of a house site.
The floor level of the house is 3m lower than the Territorial Authority sewer connection.
On the plan provided, draw and label the foul water drainage system to satisfy AS/NZS 3500 
Part 2: Sanitary plumbing and drainage. Include all pipe work, connections, ventilation, chambers,
junctions, bends, access points and any other requirements to meet the minimum requirements in
compliance with AS/NZS 3500 Part 2: Sanitary plumbing and drainage.

PLEASE SEE PDF FOR IMAGES

Total 10 marks


Linkback: https://www.plumbers.nz/drainlaying-exam-november-2008/26/question-7/210/


Share via digg Share via facebook Share via linkedin Share via twitter

Similar Topics

  Subject / Started by Replies / Views Last post
xx
Question 15

Started by LisaS

0 Replies
2183 Views
Last post February 11, 2009, 08:59:20 AM
by LisaS
xx
Question 14

Started by LisaS

0 Replies
1852 Views
Last post February 11, 2009, 08:59:42 AM
by LisaS
xx
Question 13

Started by LisaS

0 Replies
1912 Views
Last post February 11, 2009, 09:00:14 AM
by LisaS
xx
Question 12

Started by LisaS

0 Replies
1971 Views
Last post February 11, 2009, 09:01:09 AM
by LisaS
 
Share this topic...
In a forum
(BBCode)
In a site/blog
(HTML)