Plumbers NZ is New Zealand's largest online plumbing, gas and drainage resource. Plumbing exam help, plumbing news, directory and free quotes.

Author Topic: Faulty Towers  (Read 2972 times)

0 Members and 1 Guest are viewing this topic.

Offline robbo

  • Hero Member
  • *****
  • Posts: 1259
  • Karma: +83/-7
Faulty Towers
« on: June 25, 2018, 07:59:58 AM »
hi guys, have a look at what NZ plumbing has come too with latest hotel plumbing carried out in China as `PODS`this is a blot on our industry.  Have a good read you will be amazed.  Hope GAS is not going to be installed in the same way, cheers

Linkback: https://www.plumbers.nz/pgdb-new-zealand-plumbing-gasfitting-and-drainlaying-board/30/faulty-towers/2346/

Offline Plumber

  • Administrator
  • Hero Member
  • *****
  • Posts: 736
  • Karma: +52/-2
  • ***#1 Plumber***
Re: Faulty Towers
« Reply #1 on: June 29, 2018, 01:14:36 PM »
Hi Robo, you should copy paste the content into the post, the download ma trigger peoples virus software blocking it.
Please note that the advice I am giving is only my opinion and not necessarily a fact.  Please refer to our terms and conditions.

Offline robbo

  • Hero Member
  • *****
  • Posts: 1259
  • Karma: +83/-7
Re: Faulty Towers
« Reply #2 on: July 01, 2018, 09:48:22 AM »
hi  Plumber, you asked for it,cheers
...
Leak latest saga in ongoing Christchurch Airport hotel 'disaster'
A major water leak at the $82 million Novotel Christchurch Airport has those involved labelling it a "disaster".
The water leak caused significant damage, insiders say, and comes after extensive delays because of mistakes with steel and multiple problems with pre-fabricated bathroom pods.
One contractor, speaking to Stuff anonymously, said at least half the building was affected by water damage from drain pipes, including plaster board, insulation, and the lift, which needed repairing because water went down the shaft.
"There are numerous walls that need to have the [plaster board] removed to dry out properly or else there will be black mould form in the wall cavities. It does not appear they are going to do this," the contractor said. They said the project was turning into a "disaster".
READ MORE:
* Further delays for $80 million Christchurch Airport hotel
* Incorrect steel delays Christchurch airport hotel opening
* Opposition to Christchurch Airport building $80m Novotel
* Christchurch's new airport hotel part of property expansion
* Fletcher bearing costs of Christchurch justice precinct delays
The Warren & Mahoney-designed 200-room Novotel Christchurch Airport is a franchise partnership agreement between AccorHotels and developer, Christchurch Airport International Limited (CIAL), which is 75 per cent owned by the Christchurch City Council and 25 per cent owned by the Crown.
Because of an historical agreement with the airport, Sudima has the lease on the building. However, it will be run by AccorHotels as a Novotel, with the airport company retaining ownership.
Originally scheduled to open in December 2017, a mistake with steel last August delayed the hotel opening until February. Now sources on-site claim the completion date is likely to be April 2019.
A CIAL spokeswoman said it was unsure when the hotel would open and directed queries to Fletcher Construction.
"We are disappointed to have become caught up in Fletcher issues," she said. "We do not yet have a confirmed completion date and look forward to receiving that from Fletcher."
A Fletcher spokesperson said: "We are not going to discuss the specific details of the day-to-day progress or timeline of each project, or commercially sensitive information."
Stuff previously reported that pre-fabricated bathroom pods for the hotel were left in the rain. They were installed but later found to have developed extensive mould so had to be removed and completely replaced.
"Issues with bathroom pods were discovered as part of regular quality control measures at the site, and pods are being replaced to ensure a high quality build," the Fletcher spokesperson said.
Construction problems with the hotel first emerged last August when, as Christchurch Airport chief executive Malcolm Johns told Stuff, some of the New Zealand-supplied steel did not meet requirements.
Fletcher said it was supplied incorrect steel for some of the bracing elements, but this was identified on site before installation and was corrected.
The Christchurch hotel design is based on Novotel Auckland Airport, which was also designed by Warren & Mahoney. One contractor said "someone stuffed up", removing the boiler/plant room from the plan to add more rooms to the Christchurch hotel.
The design firm said it had not made any errors. "A separate plant building was part of the approved concept for the project", a spokesperson said, and directed further queries to Fletcher.
Fletcher was asked to respond to allegations that:
- The bathroom pods have cost Fletcher $6m to date. One bathroom alone cost $1m as Fletcher paid a 20 per cent deposit of $1m to a Chinese manufacturer for a prototype bathroom. The manufacturer delivered one bathroom but then "disappeared without trace" with the money, a source says. The third set of bathroom pods is now awaiting installation.
- Because it is late delivering the hotel, Fletcher is paying for full occupancy every night. One source puts this figure at "$40,000 a day" since December.
- The top floor of the hotel has been designed to use panels that are only manufactured in a square configuration, but need to be installed in an isosceles triangle shape.
- On the top floor, the air conditioning units are installed lower than the ceiling height.
- The dimensions of the building are wrong and it is 300mm too tall.
The spokesperson replied: "We are standing by our commitment to complete all our remaining Building + Interiors (B+I) projects to the highest quality, including the Novotel in Christchurch. There is no change to the provisions we announced on February 14, 2018."
On February 14, Fletcher Building announced further provisions for expected losses in its Buildings + Interiors business of $486m, leading to a total projected B+I loss of $660m in the 2018 financial year.

https://www.stuff.co.nz/business/104889096/leak-latest-saga-in-ongoing-christchurch-airport-hotel-disaster

The Press

Offline Plumber

  • Administrator
  • Hero Member
  • *****
  • Posts: 736
  • Karma: +52/-2
  • ***#1 Plumber***
Re: Faulty Towers
« Reply #3 on: July 04, 2018, 07:44:50 AM »
thanks  :)


Share via digg Share via facebook Share via linkedin Share via twitter

Similar Topics

  Subject / Started by Replies / Views Last post
xx
Faulty gas oven

Started by aboutgas

3 Replies
3494 Views
Last post August 09, 2011, 06:53:45 PM
by dodgplumma
xx
Recall of faulty gas heaters

Started by wombles

1 Replies
2316 Views
Last post September 29, 2014, 03:19:28 PM
by aboutgas
question
Faulty Cylinder or Dodgy Home Owner??

Started by Plumber

7 Replies
7004 Views
Last post September 10, 2010, 11:19:19 AM
by bulldog
 
Share this topic...
In a forum
(BBCode)
In a site/blog
(HTML)