Question 2
« on: February 11, 2009, 09:30:28 AM »
QUESTION 2
(a)  Describe how pipes in a large underground water main are prevented from moving at bends and
junctions.
(2 marks)

(b)  State THREE requirements that must be met when a water main is run in a trench with other
services.
 1
 2
 3
(3 marks)

(c)  State THREE requirements that must be met for the trenching and back-filling of a UPVC water
main.
 1
 2
 3
(3 marks)

Total 8 marks

Linkback: https://www.plumbers.nz/plumbing-exam-2006/19/question-2/142/


Share via digg Share via facebook Share via linkedin Share via twitter

Similar Topics

  Subject / Started by Replies / Views Last post
xx
Question 15

Started by LisaS

0 Replies
2183 Views
Last post February 11, 2009, 08:59:20 AM
by LisaS
xx
Question 14

Started by LisaS

0 Replies
1852 Views
Last post February 11, 2009, 08:59:42 AM
by LisaS
xx
Question 13

Started by LisaS

0 Replies
1912 Views
Last post February 11, 2009, 09:00:14 AM
by LisaS
xx
Question 12

Started by LisaS

0 Replies
1971 Views
Last post February 11, 2009, 09:01:09 AM
by LisaS
 
Share this topic...
In a forum
(BBCode)
In a site/blog
(HTML)